A. Prior to construction, any operator of a project with one acre or more of construction activities shall notify the city through the inspections department at least twenty-four (24) hours prior to initiating activities.

B. Owners and operators of construction activities shall complete a daily inspection log in the format provided by the city. Records of self-inspection shall be compiled and retained for a minimum of one (1) year or for six (6) months beyond the project duration, whichever is longer.

C. Any operator subject to the provisions of section 4-9-8 of this chapter shall notify the city within ten (10) days of completion of long term stabilization activities.

D. All required information shall be provided to the city and UDAQ representatives upon request. (Ord. 2007-12-005, 12-6-2007)